25 building variants in 13 families, plus six structures. The work register contains 217 tasks; proposed room programs still need selection and dimensioned drawings.
New / all 31 asset prep pages Open the Crown Key workbench for building-specific plans, shared kits and prop tasks. Quik’s Friday brief starts with the existing Crown Landmark candidate and its remaining decisions.
Crown Landmark / readiness report All 81 rooms are now measured: see the readiness report for the confirmed conflicts, unchecked floors and Quik’s next deliverables, and review exterior candidate C02. The district construction hold remains.
Planning status: current Unreal placement and scale require inspection. All room programs and developer assignments are proposals unless their source says otherwise. No asset is certified built by this page.
Reconcile existing INT R02, do not restart it. Test L25 +126 m and L26 +130.5 m against taper/ribs; preserve independent diplomacy access.PI-BLD-0001-V01-04 · pending
Select enterability and implement only the approved room/kit program: Existing atrium/gallery and circulation; council/vote suite, waiting, celebration, windowed corridor; diplomacy breakfast, office, private lounge and secured recordsPI-BLD-0001-V01-05 · candidate scope
Review shell fit and a furnished/player-camera sample; derive actual window/site viewsPI-BLD-0001-V01-06 · pending
Verify collision, navigation, access, streaming, materials and performance; issue manifest and current commit evidencePI-BLD-0001-V01-07 · pending
Measure the two cores and bridge levels/clearances. Review skybridge egress and shared circulation.PI-BLD-0002-V01-04 · pending
Select enterability and implement only the approved room/kit program: Paired lobbies, reusable office/residential floor, skybridge garden only if selected playablePI-BLD-0002-V01-05 · candidate scope
Review shell fit and a furnished/player-camera sample; derive actual window/site viewsPI-BLD-0002-V01-06 · pending
Verify collision, navigation, access, streaming, materials and performance; issue manifest and current commit evidencePI-BLD-0002-V01-07 · pending
Document floor rotation, stable core, facade-to-room fit and usable corner space; tall/compact are distinct envelopes.PI-BLD-0004-V01-04 · pending
Select enterability and implement only the approved room/kit program: Lobby and one typical rotated-floor office/residential kitPI-BLD-0004-V01-05 · candidate scope
Review shell fit and a furnished/player-camera sample; derive actual window/site viewsPI-BLD-0004-V01-06 · pending
Verify collision, navigation, access, streaming, materials and performance; issue manifest and current commit evidencePI-BLD-0004-V01-07 · pending
Document floor rotation, stable core, facade-to-room fit and usable corner space; tall/compact are distinct envelopes.PI-BLD-0004-V02-04 · pending
Select enterability and implement only the approved room/kit program: Lobby and one typical rotated-floor office/residential kitPI-BLD-0004-V02-05 · candidate scope
Review shell fit and a furnished/player-camera sample; derive actual window/site viewsPI-BLD-0004-V02-06 · pending
Verify collision, navigation, access, streaming, materials and performance; issue manifest and current commit evidencePI-BLD-0004-V02-07 · pending
Resolve courtyard access for V01 and glass frontage/corner modules for V02; share compatible interiors only.PI-BLD-0007-V01-04 · pending
Select enterability and implement only the approved room/kit program: Reception, typical office/meeting kit, toilets/service and courtyard route where presentPI-BLD-0007-V01-05 · candidate scope
Review shell fit and a furnished/player-camera sample; derive actual window/site viewsPI-BLD-0007-V01-06 · pending
Verify collision, navigation, access, streaming, materials and performance; issue manifest and current commit evidencePI-BLD-0007-V01-07 · pending
Resolve courtyard access for V01 and glass frontage/corner modules for V02; share compatible interiors only.PI-BLD-0007-V02-04 · pending
Select enterability and implement only the approved room/kit program: Reception, typical office/meeting kit, toilets/service and courtyard route where presentPI-BLD-0007-V02-05 · candidate scope
Review shell fit and a furnished/player-camera sample; derive actual window/site viewsPI-BLD-0007-V02-06 · pending
Verify collision, navigation, access, streaming, materials and performance; issue manifest and current commit evidencePI-BLD-0007-V02-07 · pending
Draw furnished unit plans, privacy, balconies and service access; variant envelopes are not scaled copies.PI-BLD-0008-V01-04 · pending
Select enterability and implement only the approved room/kit program: Lobby/stair, reusable apartment kit, shared terrace and service areaPI-BLD-0008-V01-05 · candidate scope
Review shell fit and a furnished/player-camera sample; derive actual window/site viewsPI-BLD-0008-V01-06 · pending
Verify collision, navigation, access, streaming, materials and performance; issue manifest and current commit evidencePI-BLD-0008-V01-07 · pending
Draw furnished unit plans, privacy, balconies and service access; variant envelopes are not scaled copies.PI-BLD-0008-V02-04 · pending
Select enterability and implement only the approved room/kit program: Lobby/stair, reusable apartment kit, shared terrace and service areaPI-BLD-0008-V02-05 · candidate scope
Review shell fit and a furnished/player-camera sample; derive actual window/site viewsPI-BLD-0008-V02-06 · pending
Verify collision, navigation, access, streaming, materials and performance; issue manifest and current commit evidencePI-BLD-0008-V02-07 · pending
Measure crescent curvature and corridor/room fit. V02 use remains a proposal; test its compact terrace envelope separately.PI-BLD-0009-V01-04 · pending
Select enterability and implement only the approved room/kit program: Reception/lounge, typical guest-room kit, public dining and selected terrace; service/laundry/loading routePI-BLD-0009-V01-05 · candidate scope
Review shell fit and a furnished/player-camera sample; derive actual window/site viewsPI-BLD-0009-V01-06 · pending
Verify collision, navigation, access, streaming, materials and performance; issue manifest and current commit evidencePI-BLD-0009-V01-07 · pending
Measure crescent curvature and corridor/room fit. V02 use remains a proposal; test its compact terrace envelope separately.PI-BLD-0009-V02-04 · pending
Select enterability and implement only the approved room/kit program: Reception/lounge, typical guest-room kit, public dining and selected terrace; service/laundry/loading routePI-BLD-0009-V02-05 · candidate scope
Review shell fit and a furnished/player-camera sample; derive actual window/site viewsPI-BLD-0009-V02-06 · pending
Verify collision, navigation, access, streaming, materials and performance; issue manifest and current commit evidencePI-BLD-0009-V02-07 · pending
Measure arcade rhythm, covered passage and shop depth. Resolve curved and corner geometry rather than stretching a straight bay.PI-BLD-0010-V01-04 · pending
Select enterability and implement only the approved room/kit program: One representative shop/cafe bay, back room, toilet/service; other bays reuse the kit or stay exterior-onlyPI-BLD-0010-V01-05 · candidate scope
Review shell fit and a furnished/player-camera sample; derive actual window/site viewsPI-BLD-0010-V01-06 · pending
Verify collision, navigation, access, streaming, materials and performance; issue manifest and current commit evidencePI-BLD-0010-V01-07 · pending
Measure arcade rhythm, covered passage and shop depth. Resolve curved and corner geometry rather than stretching a straight bay.PI-BLD-0010-V02-04 · pending
Select enterability and implement only the approved room/kit program: One representative shop/cafe bay, back room, toilet/service; other bays reuse the kit or stay exterior-onlyPI-BLD-0010-V02-05 · candidate scope
Review shell fit and a furnished/player-camera sample; derive actual window/site viewsPI-BLD-0010-V02-06 · pending
Verify collision, navigation, access, streaming, materials and performance; issue manifest and current commit evidencePI-BLD-0010-V02-07 · pending
Measure arcade rhythm, covered passage and shop depth. Resolve curved and corner geometry rather than stretching a straight bay.PI-BLD-0010-V03-04 · pending
Select enterability and implement only the approved room/kit program: One representative shop/cafe bay, back room, toilet/service; other bays reuse the kit or stay exterior-onlyPI-BLD-0010-V03-05 · candidate scope
Review shell fit and a furnished/player-camera sample; derive actual window/site viewsPI-BLD-0010-V03-06 · pending
Verify collision, navigation, access, streaming, materials and performance; issue manifest and current commit evidencePI-BLD-0010-V03-07 · pending
Define open versus enclosed areas, roof structure, water-edge safety/collision and actual access.PI-BLD-0011-V01-04 · pending
Select enterability and implement only the approved room/kit program: Sheltered public lounge/kiosk or small event room, service storage if selectedPI-BLD-0011-V01-05 · candidate scope
Review shell fit and a furnished/player-camera sample; derive actual window/site viewsPI-BLD-0011-V01-06 · pending
Verify collision, navigation, access, streaming, materials and performance; issue manifest and current commit evidencePI-BLD-0011-V01-07 · pending
Define open versus enclosed areas, roof structure, water-edge safety/collision and actual access.PI-BLD-0011-V02-04 · pending
Select enterability and implement only the approved room/kit program: Sheltered public lounge/kiosk or small event room, service storage if selectedPI-BLD-0011-V02-05 · candidate scope
Review shell fit and a furnished/player-camera sample; derive actual window/site viewsPI-BLD-0011-V02-06 · pending
Verify collision, navigation, access, streaming, materials and performance; issue manifest and current commit evidencePI-BLD-0011-V02-07 · pending
Select enterability and implement only the approved room/kit program: Open arrival shelter; no full interior. Small service/control booth only if later selectedPI-BLD-0012-V01-05 · candidate scope
Review shell fit and a furnished/player-camera sample; derive actual window/site viewsPI-BLD-0012-V01-06 · pending
Verify collision, navigation, access, streaming, materials and performance; issue manifest and current commit evidencePI-BLD-0012-V01-07 · pending
Select enterability and implement only the approved room/kit program: Open arrival shelter; no full interior. Small service/control booth only if later selectedPI-BLD-0012-V02-05 · candidate scope
Review shell fit and a furnished/player-camera sample; derive actual window/site viewsPI-BLD-0012-V02-06 · pending
Verify collision, navigation, access, streaming, materials and performance; issue manifest and current commit evidencePI-BLD-0012-V02-07 · pending
Establish envelope and facade grid for tall and slim variants; no legacy H/LM mapping by name.PI-BLD-0013-V01-04 · pending
Select enterability and implement only the approved room/kit program: Lobby, typical office/residential floor kit, service corePI-BLD-0013-V01-05 · candidate scope
Review shell fit and a furnished/player-camera sample; derive actual window/site viewsPI-BLD-0013-V01-06 · pending
Verify collision, navigation, access, streaming, materials and performance; issue manifest and current commit evidencePI-BLD-0013-V01-07 · pending
Establish envelope and facade grid for tall and slim variants; no legacy H/LM mapping by name.PI-BLD-0013-V02-04 · pending
Select enterability and implement only the approved room/kit program: Lobby, typical office/residential floor kit, service corePI-BLD-0013-V02-05 · candidate scope
Review shell fit and a furnished/player-camera sample; derive actual window/site viewsPI-BLD-0013-V02-06 · pending
Verify collision, navigation, access, streaming, materials and performance; issue manifest and current commit evidencePI-BLD-0013-V02-07 · pending
Deck/underside section, spans, supports, grades and both connection endpoints.PI-STR-0001-V01-04 · pending
Select enterability and implement only the approved room/kit program: No habitable interior; access/collision/service interfaces onlyPI-STR-0001-V01-05 · candidate scope
Review shell fit and a furnished/player-camera sample; derive actual window/site viewsPI-STR-0001-V01-06 · pending
Verify collision, navigation, access, streaming, materials and performance; issue manifest and current commit evidencePI-STR-0001-V01-07 · pending
Select enterability and implement only the approved room/kit program: No habitable interior; access/collision/service interfaces onlyPI-STR-0002-V01-05 · candidate scope
Review shell fit and a furnished/player-camera sample; derive actual window/site viewsPI-STR-0002-V01-06 · pending
Verify collision, navigation, access, streaming, materials and performance; issue manifest and current commit evidencePI-STR-0002-V01-07 · pending
Water datum, wall/top elevations, promenade clear width, accessible transitions and shoreline section.PI-STR-0003-V01-04 · pending
Select enterability and implement only the approved room/kit program: No habitable interior; access/collision/service interfaces onlyPI-STR-0003-V01-05 · candidate scope
Review shell fit and a furnished/player-camera sample; derive actual window/site viewsPI-STR-0003-V01-06 · pending
Verify collision, navigation, access, streaming, materials and performance; issue manifest and current commit evidencePI-STR-0003-V01-07 · pending
Dock length/width, deck elevation, boat envelope, piles and access from shore.PI-STR-0004-V01-04 · pending
Select enterability and implement only the approved room/kit program: No habitable interior; access/collision/service interfaces onlyPI-STR-0004-V01-05 · candidate scope
Review shell fit and a furnished/player-camera sample; derive actual window/site viewsPI-STR-0004-V01-06 · pending
Verify collision, navigation, access, streaming, materials and performance; issue manifest and current commit evidencePI-STR-0004-V01-07 · pending
Select enterability and implement only the approved room/kit program: No habitable interior; access/collision/service interfaces onlyPI-STR-0005-V01-05 · candidate scope
Review shell fit and a furnished/player-camera sample; derive actual window/site viewsPI-STR-0005-V01-06 · pending
Verify collision, navigation, access, streaming, materials and performance; issue manifest and current commit evidencePI-STR-0005-V01-07 · pending
Repeat bay span/height/depth, column/canopy joints and fit to arcade building variants.PI-STR-0006-V01-04 · pending
Select enterability and implement only the approved room/kit program: No habitable interior; access/collision/service interfaces onlyPI-STR-0006-V01-05 · candidate scope
Review shell fit and a furnished/player-camera sample; derive actual window/site viewsPI-STR-0006-V01-06 · pending
Verify collision, navigation, access, streaming, materials and performance; issue manifest and current commit evidencePI-STR-0006-V01-07 · pending
No matching assets. Clear the search or choose all collections, priorities and types.
15 October 2026 · 25 building variants in 13 families, plus six structure variants. This is a task/program register, not completed construction drawings or approval of room dimensions. Source art and imagery remain the visual blueprint; reviewed measured drawings establish physical fit.
P0: measure current Crown Key/world scale and connections; review Crown Landmark's existing EXT R06 / INT R02 shell and L18/L19 fit. P1: create reusable street-life samples (arcade shop, apartment, office, hotel/pavilion/arrival) and their routes. P2: extend proven kits to the remaining skyline variants. These priorities are a proposed work sequence; they do not force every optional interior into the first release.
The current UE commit removes building mesh assets. Source footprint counts and older “exteriors built” statements are historical; current placement needs inspection. No catalog building is certified built here.
Story requirement versus proposed world life
The current atlas identifies two Crown Key locations: PI-LOC-018 / L18, the council/vote suite, and PI-LOC-019 / L19, the diplomacy suite. Crown Landmark is their proposed host; parcel, shell and level assignment remain unapproved. V2.1 supplies repeated failed meetings and commissioning/celebration candidates; the novel supplies its separate vote, private pressure and corridor requirements. Preserve scene-era/status distinctions. Do not assign every landmark an invented story function or identify five headquarters by tower resemblance.
For Crown Landmark, continue the existing design: verify council/waiting/celebration/view corridor on proposed L25 and breakfast/private office/lounge/secured records on L26, plus atrium/gallery and circulation. Check taper/ribs at +126/+130.5 m, three passenger lifts, two stairs, service shaft and intervening floors, L02 overlook headroom, observer sightlines, voting controls, privacy, acoustics and doors. The 81-room / 102-door proposal includes circulation/service records; it does not mean 81 unique hero interiors.
Other interiors below are candidate everyday uses. Choose enterability before generating images. Tier C kits repeat; an unselected tower may remain Tier A. Canopies and structures have no automatic interior scope.
Drawing and acceptance checklist for every selected building
Dimensioned ground/roof plan; every distinct playable floor or typical plan plus repeated-level list; facade elevations and sections through core/structure/terraces.
Envelope and level schedule: widths/depths/heights, wall/slab thickness, clear heights, taper, core/shafts and roof/crown.
Room/door/window schedules and furniture plan: usable dimensions, door swings, circulation, player/camera envelope and access/privacy/service routes.
Reviewed shell, selected interior kit, short primary image list, materials/components and placement-specific deviations.
Furnished gameplay sample and actual placed-window views; collision/navigation/streaming/performance checks with commit/map evidence.
Handoff README, source files, IDs/revisions, change log, manifest and unresolved decisions. Keep template completeness separate from design/engine approval.