  "id": "CK-PILOT-EXECUTION",
  "revision": "R01",
  "recorded_at": "2026-10-16T23:07:37Z",
  "timezone": "America/New_York",
  "baseline_main": "4ce28d89b6fb1922f0b8427937b986961504307d",
  "web": "/production/team-plan/pilot/",
  "status": "historical_pilot_with_current_status_reconciliation",
  "authorization": "Legend explicitly approved main publication and ordinary follow-ups for the current Crown Key pilot/preparation phase at 19:00 America/New_York on 16 October 2026. No repeated approval request is needed within this phase. Proposed/test-only inputs, concept review, asset acceptance and world-construction gates retain their own status.",
  "freshness": "Original pilot evidence is dated 16 October. Reconciled against main 4ce28d89 on 17 October UTC: PRs #45/#51 are merged. R02 controls current five-seat work; this record is not live telemetry or engine acceptance.",
  "tasks": [
    {
      "actor": "Codex orchestration",
      "status": "in_progress",
      "work": "Integrate design inputs, concepts, agent findings and the pilot handoff.",
      "evidence": [
        "README.md",
        "SAMPLE_INPUT_PROPOSAL.json",
        "IMAGE_RECORD.json",
        "TERRACE_IMAGE_RECORD.json"
      ]
    },
    {
      "actor": "Sample review agent",
      "status": "completed",
      "work": "Review written geometry, route connectivity and import ambiguities; recheck the amended R02 proposal.",
      "evidence": [
        "SAMPLE_REVIEW.md",
        "SAMPLE_SCHEMA_MAPPING_REVIEW.md"
      ],
      "result": "R02 is internally coherent as a proposed disposable scene; no generated geometry or engine test performed. Follow-up mapping against PR #51 documents exact known values, unknowns and floor/scope reconciliation; no second contract or generated geometry was authored."
    },
    {
      "actor": "Terrace research agent",
      "status": "completed",
      "work": "Audit current source records/catalog and write invariants, core/setback questions and required evidence.",
      "evidence": [
        "TERRACE_REFERENCE_REVIEW.md"
      ],
      "result": "Source-backed research complete; no dimensions, accepted scope or shell created."
    },
    {
      "actor": "Tooling reconciliation agent",
      "status": "completed",
      "work": "Check remote branch/PR evidence and identify the generic-fixture dependency and shared path conflicts.",
      "evidence": [
        "CLAUDE_NEXT.md"
      ],
      "result": "Historical checkpoint: No published contract-pilot branch/schema/fixture observed; pending C02 PR #45 is a separate workflow. Superseded status: PR #51 and PR #45 subsequently merged; retain the earlier observation as dated research evidence."
    },
    {
      "actor": "Claude tooling",
      "status": "completed_merged_unreal_pending",
      "work": "Checkpoint A/C: path claims, schema/migration, asymmetric fixture, drawing/blockout commands and test-only release rejection.",
      "evidence": [
        "CLAUDE_NEXT.md"
      ],
      "result": "Claude contract-pilot PR #51 is merged into main (merge 7a81eb8, head 3701c09), including reviewed R02 mapping, deterministic drawings/blockouts/cameras and the TEST-ONLY Quik import package. Manifest SHA-256 a232289bb781ada7fed5718b8b660a2834e4cc471ac2d8dc6ddeecbdfe578aac. Quik’s actual Unreal results remain pending. Both test contracts remain refused by the production issue gate; automatic production packaging integration is still a separate task.",
      "historical_review_result": "Claude contract-pilot PR #51 is published at 3a330788a840e6757bd47cee4e0731c08499478f with green Verify checks. Independent review reproduced four validator/drawing corrections and a floor/scope mapping dependency. Keep #51 open pending focused fixes and recheck; R02 mapping and Quik’s actual Unreal test remain open."
    },
    {
      "actor": "Quik engine test",
      "status": "pending_external_test",
      "work": "Confirm actual software/import settings, scale/orientation, collision, character/camera envelope and traversal.",
      "evidence": [],
      "result": "No new Blender/Unreal execution or engine acceptance claimed by this packet."
    },
    {
      "actor": "Independent contract-tooling review",
      "status": "completed_rechecked_merged",
      "work": "Run the pinned PR #51 contract suite and focused validation/drawing probes in an isolated text-only audit.",
      "evidence": [
        "TOOLING_REVIEW.md"
      ],
      "result": "Historical review at 3a330788 reproduced four corrections. PR #51 subsequently corrected them, passed Codex’s recheck and merged at 7a81eb8. The historical findings remain preserved; no independent Unreal execution is claimed.",
      "historical_review_result": "46 tests run, seven Blender tests skipped; four issue-gate/drawing corrections reproduced. #51 remains open; no independent Blender/Unreal execution."
    }
  ],
  "next_sequence": [
    "The current five-seat production plan is at https://thelostsouls.world/CrownKey/production/plan/ and docs/crown-key-production/R02/AI_START_HERE.md. Three OpenAI seats and two Claude seats work in parallel: Quik starts Crown Landmark authoring/staging while the team completes Split Complex and Terrace Tower packages. Every enclosed building receives a lobby plus one or two useful interior spaces, with Atlas scene requirements taking priority. Open structures receive appropriate arrival and access spaces. R01 remains technical and historical support.",
    "Use merged PR #51 tools and the sealed TEST-ONLY fixture/sample package; Quik records actual importer and traversal evidence.",
    "Reconcile Split H1 with the older Candidate B technical structure, then author proposed production geometry and complete lobby plus selected interiors.",
    "Advance Terrace Tower concurrently and feed measured tooling/engine findings into both packages.",
    "Support Crown Landmark decisions from merged C02/all-room fit evidence; keep shell, world placement and engine acceptance separate."
  ],
  "publication": {
    "pr": 50,
    "branch": "codex/crown-key-design-inputs-r01",
    "state": "merged_main",
    "merge_sha": "6fa4e05f98a18b41a845a5ca96109f4bb5745efc",
    "phase_authorization": "Creator-authorized main publication for this phase on 16 October 2026 at 19:00 America/New_York. Automatic rejection before this clarification is historical."
  },
  "tooling_pr": {
    "number": 51,
    "head": "3701c0961c4399564d2a0019e4efd279d5ac0709",
    "branch": "claude/crown-key-contract-pilot-r01",
    "url": "https://github.com/215GrandAve/lost-souls/pull/51",
    "status": "merged_quik_unreal_results_pending",
    "merge_sha": "7a81eb8e741aacc119cb22aa682ae679162f9804"
  },
  "historical_snapshot": {
    "recorded_at": "2026-10-16T23:07:37Z",
    "baseline_main": "aa3b95526ce18bd7c74cc0a232c62e1b0f82535b",
    "description": "Original R01 pilot checkpoint; task-level historical findings below remain dated."
  },
  "reconciled_at": "2026-10-17",
  "current_plan": {
    "web": "/CrownKey/production/plan/",
    "repo": "docs/crown-key-production/R02/AI_START_HERE.md",
    "summary": "The current five-seat production plan is at https://thelostsouls.world/CrownKey/production/plan/ and docs/crown-key-production/R02/AI_START_HERE.md. Three OpenAI seats and two Claude seats work in parallel: Quik starts Crown Landmark authoring/staging while the team completes Split Complex and Terrace Tower packages. Every enclosed building receives a lobby plus one or two useful interior spaces, with Atlas scene requirements taking priority. Open structures receive appropriate arrival and access spaces. R01 remains technical and historical support."
  },
  "crown_landmark_update": {
    "number": 45,
    "status": "merged_design_and_engine_acceptance_separate",
    "merge_sha": "a7220dbd752382b0ca5f4f929335405d6588e505",
    "summary": "PR #45 is merged into main at a7220dbd752382b0ca5f4f929335405d6588e505 (2026-10-17 02:17:42 UTC). C01 is preserved; C02 and all-81-room fit measurements are available. C02 records 75 fits, five rooms inside but below the proposed 1.2 m allowance, and one outside wall and deck. All 32 L25/L26 rooms fit in C02. Lower atrium/gallery clearance, L03-RM001/Rib_R1, taper and allowance decisions remain open. Publication is not shell or engine acceptance."
  }
}