# Crown Landmark — Quik shell and layout work order

**Asset:** PI-BLD-0001-V01 · **Status:** prepared for coordination; execution and acceptance not claimed.  
Use [START_HERE](START_HERE.md) first. Check any active construction hold and permitted scope before starting model work. This work order prepares the evidence needed to resolve the building; it does not authorize changes to district geography or release a separate hold.

## Deliverable

One identifiable, editable shell and a measured fit review of the retained INT proposal. Begin with plain geometry. Keep facade/crown/ribs, podium, core and room zones separately identifiable. Resolve dimensions and connections before detailed meshes or additional image generation.

## Inputs and reference rules

- [EXT_R06 brief](../SOURCES/PI-BLD-0001-V01_CrownLandmark_EXT_R06/04_Handoff/MODELING_BRIEF.txt) and [design-target JSON](../SOURCES/PI-BLD-0001-V01_CrownLandmark_EXT_R06/05_ScaleAndPlan/PI-BLD-0001-V01_CrownLandmark_EXT_R06_DesignTargets.json).
- [INT layout JSON](../SOURCES/PI-BLD-0001-V01_CrownLandmark_INT_R02/06_Handoff/EditableLayout/INTERIOR_LAYOUT.json), [room schedule](../SOURCES/PI-BLD-0001-V01_CrownLandmark_INT_R02/06_Handoff/ROOM_SCHEDULE.csv), [door schedule](../SOURCES/PI-BLD-0001-V01_CrownLandmark_INT_R02/06_Handoff/DOOR_SCHEDULE.csv) and source SVG sheets in `04_PlansAndSections`.
- [Planning OBJ limitations](../SOURCES/PI-BLD-0001-V01_CrownLandmark_INT_R02/06_Handoff/EditableLayout/README.txt). Rebuild coherent geometry from the layout; do not treat the OBJ as finished walls or collision.
- [Reference authority](REFERENCE_AUTHORITY.csv). Front/master govern silhouette; `02_Rear` governs the rear. Use plans for proposed geometry when perspectives disagree and log the mismatch.

## Required measured review

1. **Record source identity and coordinates.** Save native filename, revision, tool/version and units. Keep actor/component scale at 1 unless a reviewed exception is recorded. Source proposal uses metres, Z up, tower-centred origin, X local right, front negative Y. Record any conversion to the destination tool explicitly. Verify a known dimension after import; do not assume the import scale is correct.
2. **Measure the shell.** Compare actual results to proposed 240 m height,160 × 120 m foundation, podium decks +18/+36/+54 m, tower base 68 × 54 m, roof +216 m and crown to +240 m. Record usable clear heights, wall thickness, structural intrusions and roof/foundation extents; unknowns remain null with an owner. Record measured values and differences; do not change the proposed record silently. Entrance targets are arch 18 m wide/14 m clear and portal 8 m wide/4.5 m clear.
3. **Check the same model from every side.** Export front,rear,left,right,vertical overhead and elevated views with scale cues. Identify the model revision on every sheet. Confirm the rear override and principal ribs. Perspective images cannot substitute for orthographic dimensions.
4. **Prove upper-floor fit.** Section at L25/+126 m and L26/+130.5 m. Overlay all room zones, circulation, core, facade thickness and ribs on the actual usable shell. The proposals span approximately60 × 40 m and60 × 48 m respectively; the68 × 54 m envelope is only defined at tower base. Report intersections and missing clearance without assuming the taper fits.
5. **Prove atrium and circulation fit.** Review L00/+0,L01/+6,L02/+12 and L03/+18 together. Check omitted central slabs,14 m atrium clear height,L02 overlook/ceiling condition, gallery edge protection and door headroom. Verify three passenger lifts,two stairs and separate service reserve connect through intervening levels. Produce a practical player-route walkthrough once the movement capsule/settings are specified. Record staircase headroom and landing/door conflicts. Include character capsule and camera envelope, door swings, lift cab/landing clearance and furniture clearance; test one furnished sample. Cover every accessible area in plan/schedule records, and list repeated-floor instances rather than inventing coverage from a typical plan.
6. **Separate site decisions.** Do not invent parcel coordinates or rotate the city to fit reference imagery. Record district instance, accepted transform and entrance orientation when available. Keep final window views deferred until placement and actual cameras exist; use clear glazing and explicitly labeled temporary background treatment.

## Naming and return folder

Retain `PI-BLD-0001-V01`; pack revision and geometry variant are different concepts. Do not rename source EXT_R06/INT_R02 files. Follow the current global naming guide for production outputs. At minimum, every returned file must identify asset, scope, revision and role; include a short manifest mapping actual names to their purpose.

Return the native editable model, an agreed exchange export, measured comparison table, ground/roof/distinct playable-floor plans, required sections, same-model review views, room/door/window/component schedules, fit/clash notes and decision requests. Record base shell/revision, reusable interior kit and appearance preset; unknown assignments stay pending. A decision request must state the affected IDs, reference, conflict, proposed resolution and impact. Proposed dimensions remain proposed until a named decision is recorded; modeled or measured values are separate evidence states.

## Review and acceptance

An independent reviewer checks the model evidence against the controlling references and dimensions. Legend reviews visual intent and accepts the selected scale; Quik or the assigned engine owner verifies technical implementation. Record reviewer,date,model revision,evidence and outcome for every gate. An unexplained mismatch is an open issue; no numerical tolerance is invented by this work order.

Shell acceptance requires coherent measured geometry, a resolved or explicitly accepted room/core fit and recorded decisions. Engine acceptance is a later gate requiring the agreed target environment, usable import, collision/movement checks, material/texture dependencies and agreed performance budgets. Record engine version, commit, map, machine and settings with evidence. Verify pivot/orientation, walkability, stairs/doors/lifts, sightlines, lighting, LOD/HLOD and navigation as well as agreed performance. Do not certify the building from renders alone.